Good
afternoon Sunset Drive and Ransom Street Business Owners - In hopes of continued transparency I would
like to begin monthly or sooner updates with regards to the construction taking
place. In this email you will find work accomplished in the past 30 days
along with a work plan for the next 30 days. Also, so additional
coordination items will be included.
4th
of July work schedule – Iron Mountain will work as normally scheduled Monday(1st)
– Wednesday(3rd) of next week. All work will stop for Thursday
the 4th through Sunday the 7th of July.
-
An asphalt binder will be placed along the remaining gravel
areas prior to Wednesday July 3rd.
Here
are the detailed minutes of the latest progress meeting:
WORK
COMPLETED PREVIOUS MONTH
Mr.
Sam Icenhour (Iron Mountain) reviewed the previous work completed the last 30
days.
•
Completed all the 12” & 8” sewer main on Sunset Drive.
•
Installed 75% of all sewer service laterals.
•
Installed concrete sidewalk and curb & gutter along the south side of
Sunset Dr adjacent
to
the First Baptist Church and up to Ransom Street.
•
Placed temporary asphalt binder in trench in front of the Alpine Village to try
and help
minimize
dust.
•
Installed 100 LF of 6” Water Main across the box culvert on the north side of
Sunset Dr.
•
Placed permanent asphalt binder between box culvert & Ransom Street.
•
Installed the retaining wall on the south side of Sunset Dr.
WORK
SCHEDULED UPCOMING MONTH & SCHEDULE UPDATE
Mr.
Icenhour reviewed the work forthcoming the next 30 days.
•
Install the proposed retaining wall on the north side of Sunset Dr.
•
Continue & complete the sewer laterals.
• Continue with the 6” water
main installation
Continue with the asphalt
binder placement in the sewer line trench.
• Continue with the concrete
sidewalk and curb & gutter placement.
COORDINATION
ITEMS
Mr.
Doug Chapman (McGill) requested that Iron Mountain be mindful of the NCDOT’s
landscaping
activities
taking place along Valley Blvd, and to coordinate with Mr. Johnathon Walker
with
Piedmont
Landscaping if needed regarding the proposed 6” water line tie in along Valley
Blvd.
Discussions
took place regarding the number of complaints the Town has received about dust.
Mr.
Sam Icenhour stated that a water truck is being used to try a help minimize the
dust issues.
Mr.
Curtis Baker stated that the water truck shall run continuously throughout the
day when there
is
no rain scheduled. Mr. Sam Icenhour stated that traffic speeds seem to be a big
part of the
dust
issues, and it would help if the Town could have Sunset Drive policed
throughout the day to
help
minimize speeds. Mr. Shane Fox stated that the Town would start with placing a
police car
onsite
close by in an attempt to get the public to slow down. Mr. Icenhour also stated
that asphalt
binder will continue to be
placed so that the water truck can be minimized.
Thank you for your continued
support as we work to better our town!
Please do not hesitate to
contact me with any questions or issues.
Shane Fox
Town Manager
Town of Blowing Rock
1036 Main Street
PO Box 47
Blowing Rock, NC 28605
828-295-5200 (Office)
828-295-5202 (Fax)
No comments:
Post a Comment